Latest Progress in Floatover Technologies for Offshore Installations and Decommissioning
Alan M. Wang, Xizhao Jiang, Changsheng Yu, Shaohua Zhu, Huailiang Li, Yungang Wei
Installation Division, Offshore Oil Engineering Co., Ltd.,
Tanggu, Tianjin, China
ABSTRACT
This paper presents a comprehensive overview of various floatover
technologies based on the latest advancements in offshore installation
and decommissioning technology. Each floatover methodology is
briefed and categorized into specifically defined divisions in a system
of classification, including mechanical and non-mechanical schemes,
single-barge, catamaran-barge and twin-barge schemes, etc. The
presentation of these various floatover technologies will reveal the
floatover history and evolution, the advantages and disadvantages of
different methods, as well as the promising prospect of their wide
applications in installation and decommissioning of integrated topsides
onto and from various fixed and floating substructures.
KEY WORDS: Floatover technology; Hi-Deck, Smart-Leg®; Strand
Jack Lifting; TML®; Unideck®; Versa-Truss®.
NOMENCLATURE
AHTS = Anchor Handling Tow Supply (tug)
DP = Dynamic Positioning
DSF = Deck Support Frame
DSU = Deck Support Unit
FPSO = Floating Production Storage Offloading
GBS = Gravity Base Substructure
GPS = Global Positioning System
LMU = Leg Mating Unit
LSF = Loadout Support Frame
TLP = Tension Leg Platform
TML = Twin Marine Lifter
INTRODUCTION
Various floatover technologies have been developed and successfully
applied to offshore installations of integrated topsides onto different
fixed and floating platform substructures since the first floatover
installation was successfully adapted for the production platform
topsides of 18,600 tonnes on the Phillips Maureen Project in 1983. A
string of offshore facilities using the floatover concept followed,
including jackets, gravity base platforms, tension leg platforms,
semisubmersible platforms, and even spars lately.
The floatover technology is an offshore topsides installation method
that lets large platform topsides be installed as a single integrated
package without the use of a heavy lift crane vessel, i.e. modular lifting
installation. This allows the integrated topsides to be completed and
pre-commissioned onshore prior to loadout, thus eliminating the
substantial costs associated with offshore hook-up and commissioning.
For the past two decades, the floatover technology has advanced so
much from the conventional “Hi-Deck” scheme with leg mating units
to numerous floatover techniques with active/passive load transfer
systems and different configuration of floatover barge(s), thus
providing an installation solution that can accommodate a wide range
of topsides sizes and seastate conditions. These floatover techniques of
every hue include the use of the smart-leg technology with active
hydraulic devices to neutralize vertical impact, the versa-truss boom
technology with A-frame booms and multi-winching operations, the
strand jack lifting technology, or the hydraulic jack lifting technology
to raise floatover decks to the required in-place elevation at offshore
sites. In addition, single floatover barge, catamaran barge, or twin
barges have been used to meet the different configuration of
substructures, which include future floatover technology of SeaMetric’s
TML technique with twin-barge configuration using TML lifting beams
with ballast tanks and buoyancy tanks and Pieter Schelte’s single lifting
technique with catamaran configuration using hydraulically operated
lifting clamps, and so forth.
A comprehensive overview of present floatover technologies based on
the latest advancements in offshore installation and decommissioning
technology is presented hereinafter. The systematic category of various
floatover technologies defines the two major flaotover methods, that is,
the mechanical method when using active load transfer system and/or
separation system and the non-mechanical method when using passive
load transfer system and/or separation system. In addition, the floatover
technologies can be categorized into specifically defined divisions
based on the configuration of floatover barge(s), namely single barge
scheme, catamaran barge scheme, and twin barge scheme, respectively.
The advantages and disadvantages of different floatover technologies
are also addressed here.
PAST, PRESENT & PERSPECTIVE
For the past 27 years, many different kinds of floatover technologies
have been developed and successfully applied to offshore installations.
The conventional "High-Deck" or topsides floatover methodology was
initially introduced by KBR, then Brown & Root, in 1977 at the BP's
Magnus Field in the North Sea. The first floatover installation was
successfully applied to the 18,600Te integrated topsides on the
Maureen Project in 1983, whose mating operation was engineered and
performed by KBR UK. Following the Maureen Project's success,
floatover technologies, as an effective installation method, have been
widely applied to heavier integrated topsides, such as the world-record
28,800Te PA-B gas production topsides offshore Sakhalin Island, and
swell dominant conditions and harsher environments, such as West
Africa, West Austria, South China Sea, etc. However, a combination of
deep water, rough open sea, or swell conditions still pose a challenge to
provide a cost effective solution in offshore installations. A dozen of
mechanical or non-mechanical floatover technologies with different
configurations of single barge, twin barges, or catamaran barge have
been developed for various fixed and floating substructures in
challenging environments.
There are a number of reasons why the floatover method is becoming
the preferred installation method for integrated topsides, rather than
using heavy lift vessels. The availability of such heavy lift vessels is
very limited. Waiting for one suitable crane vessel to come online can
cause significant project delays. Since the majority of heavy lift vessels
are typically home-based in European waters, the mobilization and
demobilization costs can be too costly for projects in Asian-Pacific
waters. Only a handful of crane vessels have the capacity to carry out
large heavy lifts, and their day rates are very high. In addition, different
from modular installations, the primary objective with floatover
installations is to minimize costly hook-up and commissioning periods
offshore. This allows freedom of equipment layout within the deck
compared to modular lifting designs, and also completion of testing and
pre-commissioning onshore. The result is a significant reduction in
overall development cost through a shorter offshore commissioning
phase without using expensive, heavy lift crane vessels.
Fig. 1: Floatover Installation of Lun-A Topsides with T-Shaped Barge
Traditionally the floatover method is particularly suited to conditions
found in the shallow and benign water area, such as Bohai Bay, China,
refer to Liu et al. (2006), and offshore Sakhalin Island, Russia.
Therefore, the substructure design tends to be a conventional jacket
type or GBS type that favors the conventional floatover method. In
2009 four floatover installations were successfully carried out in Bohai
Bay alone where three integrated topsides ranging from 6500Te to
11,000Te were installed onto jacket substructure by a conventional “Hi-
Deck” installation and one 3000Te topsides was installed directly onto
pre-installed piles in an extremely shallow water by the strand-jack
lifting floatover scheme. The 21,800Te Lunskoye-A (LUN-A) gas
production topsides and 28,800Te Piltun-Astokhskoye (PA-B) gas
production topsides were successfully installed onto concrete GBS
structures in the Sea of Okhotsk, northeast of Sakhalin Island in June
2006 and July 2007, respectively, setting a new record as the industry's
heaviest floatover deck installation, although a 39,000Te Hibernia
topsides was installed onto a GBS using a twin-barge configuration in
protected waters offshore Newfoundland in early 1997. Nowadays the
topsides weight does not significantly affect the floatover procedures or
systems. See Fig. 1 for an example.
In the early of 1980s two North Sea projects, i.e. Phillip's Maureen and
Conoco's Hutton, placed integrated topsides on steel GBS and TLP
substructures in relatively sheltered areas and inshore shallow locations.
Recently floatover technology can be employed from shallow water to
deep water in swell conditions or harsher random waves. Moreover, the
floatover substructures can cover almost all types of existing fixed and
floating systems, including jackets, GBSs, TLPs, SEMIs, compliant
towers, and spars, except FPSOs.
The primary design concerns are fixed platforms or floating platforms
with a secondary emphasis on shallow water or deep water, as well as
benign environments and harsh sea conditions. The installation
engineering scope-of-work comprised conceptual design, engineering
and planning the entire operation, including loadout, seafastening,
transportation and installation. Perhaps even more important in terms of
ultimate cost savings for the client is early involvement during the
conceptual design phase. Early design decisions for the float-over
method can generate considerable savings further down the line. By
being involved during the conceptual and detailed design phases, naval
architects and structural engineers can provide invaluable input before
construction begins. This minimizes the need for costly changes later
on. Detailed planning for topsides transportation and subsequent
installation also enables hook-up and commission operations to begin
earlier.
Originally conceived to address the problem of making heavy lifts in
remote locations, floatover techniques are increasingly being applied to
smaller and smaller topsides. Even in regions where suitable crane
vessels are available, specifying an integrated topsides for a floatover
installation opens the market to those contractors without access to such
crane vessels, thereby providing a degree of additional competition
during project tendering. The state-of-the-art technology of floatover
installations will be further developed to improve workability, reduce
structural requirements, as well as standardize to avoid the early
commitment. Refer to Seij (2007) and O’Neill (2000) for details.
FLOATOVER PROCEDURES
Typical floatover operations may be divided into the following major
stages:
Loadout: Upon weighing, the integrated topsides will be jacked up by
a mega jacking system of hydraulic cylinders or lifted by strand jacks
before a tall DSF/LSF can be inserted under the topsides prior to
loadout operation. Topsides may be skidded onto pre-selected floatover
barge longitudinally, or laterally if longitudinal strength is limited, via a
pulling system of strand jacks or Self Propelled Modular Transporter
(SPMT) trailers with a sophisticated ballast spread.
Transportation: Once completing the seafastening and floatover
preparations, and most of all meeting the sailaway criteria, the barge
laden with the topsides sails from fabrication yard to offshore site. The
floatover tiedown design is unique and usually consists of two different
sections, i.e. the first section connecting the topsides and DSF around
DSUs, which will be removed prior to mating, and the second section
connecting DSF and barge deck, which will remain until deck cleaning.
Where a twin-barge configuration of transportation is required, such as
for spar platforms and narrow compliant towers, special transportation
and seafastening design should be developed to meet different
requirements of rigid, flexible, and even hinged connections between
twin barge and the topsides.
Pre-Floatover Preparations: Upon arrival at site, the barge is
connected with a pre-installed docking/positioning mooring system via
AHTS tugs. While in stand-off position, pre-floatover preparations are
performed including set up and function test of GPS positioning
monitoring system, motion monitoring system, environmental measure
system, soft-line rigging preparations, barge and substructure
preparations, and so on.
Docking Operation: By operating mooring winches and/or positioning
AHTS tugs, the barge will be positioned and aligned with the
substructure slot. For a configuration of twin barges or a catamaran
barge, the barge(s) will be positioned and aligned with the substructure
in middle. With the help of soft-line rigging arrangement, the barge(s)
will be docked inside the substructure slot or around the substructure
when twin barges or a catamaran barge is adopted. One main towing
tug can be used for docking operation while workboats or zodiacs may
be used for soft-line handling.
Mating Operation: Upon aligning stabbing cones with support
receptacles, the barge will be ballasted or active hydraulic devices will
be used to transfer the topsides load from the barge onto the
substructure. The load transfer system generally comprises different
sets of multi-stiffness, multi-stage LMUs, which are self-contained and
designed for each leg with different stiffness based on the leg load
transfer at different stage. The load transfer systems are basically same
for fixed or floating substructures. The major difference is that the
stiffness required for floating substructures is dominated by small
relatively small water-plane area of substructure and their free floating
motion characteristics. Special multi-stiffness, multi-stage units may be
required when large relative motions between deck and substructure are
predicted. Many different kinds of mechanical devices have been
invented to facilitate the load transfer system, thus minimizing the
impact load during mating. Depending on the site condition and
installation window requirement, typical limiting sea states for
floatover operation are given as follows:
Head Seas Beam Seas Quartering Seas
Wave Height (Hs) 1.5m 0.8m 1.2m
Wave Period (Tp) 5 - 10 sec 4 - 7 sec 5 - 8 sec
1-Min Mean Wind
Speed at EL(+) 10m
10m/sec 10m/sec 10m/sec
Surface Current 1.5m/sec 1.5m/sec 1.5m/sec
Separation & Undocking Operation: Having transferred the topsides
load, the barge continues ballasting until safe clearance between the
topsides structure underside and the DSF upside has been achieved.
Then the barge will be withdrawn from the substructure slot. DSU is a
conventional passive elastomeric separation unit which is designed to
provide an increasing gap between DSF and topsides through the load
transfer process until separation occurs. There is no steel to steel
contact during separation while the elastomeric units absorb incidental
vertical and lateral contact energy. Active separation devices may be
employed. Some of the active separation devices may provide exciting
separation event, or even explosive separation event. The basic
separation system is the same whether for fixed or floating structures,
subject to the same multi-stiffness usage as LMUs.
PRIMARY EQUIPMENT SYSTEMS
The equipment systems required for the floatover operations have
varied functions and applications. Each equipment system provided is
designed to ensure that the overall operation is executed in a safe,
timely and efficient manner, while complying with all contractual
obligations. The design of these critical installation devices plays a
crucial role in ensuring successful floatover operations. The following
provides a summary overview of the primary systems:
Floatover Barge(s): Upon loadout, the barge will transport the topsides
to site and floatover install the topsides onto a pre-installed fixed
substructure offshore or a floating substructure in place or inshore.
AHTS/Harbor Tugs: The positioning tugs including AHTS and harbor
tugs work with a mooring system and a soft-line winching system to
form a positioning spread, thus providing longitudinal and lateral pull
control during docking and undocking. AHTS tugs are also used to pre-
install the mooring system and to hook up the pre-installed mooring
lines with mooring winches upon arrival of floatover barge(s). AHTS
can also work as a positioning spread to position floating substructure
during floatover installation.
DSF/LSF: The topsides will be placed on a high transportation frame,
normally a truss frame, for its journey to the offshore site. This frame
together with the existing height of the barge, i.e. freeboard, will allow
the stabbing legs of the topsides to clear the top of the LMUs, if pre-
installed on the substructure, immediately prior to mating the two
structures.
Docking/Positioning System: In shallow water a spread mooring
system equipped mooring winches on barge deck, in combination with
soft line positioning winches also on barge deck and positioning AHTS
tugs, can function adequately to perform barge approach, initial entry,
docking and undocking operations. In deep water precise positioning
AHTS tugs in combination with soft line winches may be adequate.
The soft line positioning winching system is mainly used to suppress
surge and sway motions within the slot. When DP vessel(s) are used in
floatover installation, such docking system may be eliminated.
LMU & DSU: LMUs are designed to buffer the impact load between
the support receptacles and the mating cones during mating while
DSUs are used to buffer the impact load between the DSF and the
integrated topside during separation. LMU makes soft initial contact
and reduces relative motions before engaging to increase stiffness for
final load transfer. LMUs are specialized leg and deck mating units that
act as shock absorbers as the vessel is ballasted down and the topsides
load transfers from the deck support structures onto the substructure.
The units are custom designed for each leg of the deck to balance deck
load through load transfer and motion compensation. The heave
stiffness of each leg is designed to meet the exacting stiffness and
deflection characteristics required. Additionally, the load transfer units
are designed to have the proper stiffness to absorb initial impact energy
and any unsuppressed surge and sway energy due to environmental
forces. The design of the units has been developed over two decades of
experience and employs exacting elastomer mixing, molding, and
bonding techniques in the fabrication.
Fendering System: In general three types of fendering systems should
be provided for docking and undocking operations, i.e., sway fenders,
surge fenders, and stern guide fenders. The sway fenders can be
installed along the barge sides or on the substructure slot insides to
protect barge and substructure from direct impact while a minimum
transverse clearance may be used to limit lateral movement of the barge
and align the LMU mating cones and support receptacles transversely.
The surge fenders work as longitudinal stoppers to align the LMU
mating cones and support receptacles longitudinally and also used to
prevent direct impact between support legs and fender system at final
position. The stern guide fenders are constructed to assist the initial
docking of the barge into the structure slot to smooth the initial entry
and also protect the structure legs.
Positioning Monitoring System: A DGPS positioning monitoring
system shall be set up in the operation control room located on barge
deck. Throughout docking, mating and undocking operations the
relative position between barge and substructure shall be continuously
monitored by a GPS positioning system and visual observation.
Motion Monitoring System: Throughout the floatover operation the
barge